ARGENTINIS V. GOULD
    
      592 A.2d 378 (Conn. 1991)
    
      NATURE OF THE CASE: Gould (D) appealed an affirmation of a decision that D substantially 
      breached a contract to Argentinis (P) but still allowed P to recover damages unreduced by 
      the outstanding balance of the contract price. 
    
      FACTS: D contracted to build a house for P. P agreed to pay d a total of $344,000: 
      $294,000 in cash as the construction progressed, and $50,000 by a promissory note secured by 
      a purchase money mortgage. On the date of the transfer of title in April, 1981, P was unable 
      to move into the house because D had not completed various items of construction. The 
      parties then executed a supplemental agreement and reduced the total contract price by $4000 
      to $340,000. The parties also 'annulled' the original note and P agreed to execute a 
      substitute note and purchase money mortgage in the amount of $43,000, to be held in escrow 
      along with a $3000 cash payment by Ps pending D's completion of certain specified items of 
      construction. In July, 1981, P moved into the house. The escrowed cash and documents were 
      released leaving an unpaid balance of $43,000 under the contract. Some of the items of 
      construction specified in the supplemental agreement, however, remained incomplete. P also 
      discovered numerous defects in the structure and substructure of the house. D refused to 
      make repairs and P then refused to make payments on the mortgage. P sued D alleging that D 
      had not substantially performed the contract and seeking damages for breach of contract. P 
      commenced the second underlying action to foreclose the mortgage alleging that P had 
      defaulted in payment. The referee found that D had breached the contract by failing to 
      render substantial performance. The referee awarded P $73,068.75 in damages measured by the 
      cost of repairing the construction defects. The referee also found in favor of P on D's 
      foreclosure on the ground that D's failure of substantial performance defeated his right to 
      recover the balance of the contract price and hence his right to foreclose the mortgage. D 
      appealed to the Appellate Court, which affirmed. D appealed.
    
ISSUE:
RULE OF LAW:
HOLDING AND DECISION:
LEGAL ANALYSIS:
Get 
      free access to the entire content for Mac, PC or Online
for 2-3 days and free samples 
      of all kinds of products.
for 2-3 days and free samples of all kinds of products.
https://bsmsphd.com
© 2007-2016 Abn Study Partner
No comments:
Post a Comment