COUNTY COMMISSIONERS V. J. ROLAND DASHIELL & SONS, INC.
747 A.2d 600 (2000)
NATURE OF THE CASE: County (D) appealed a decision reversing a trial court's grant of
summary judgment for D on a quasi-contractual claim for unjust enrichment and reversing the
determination that an affidavit in opposition to the motion was defective.
FACTS: On February 22, 1994, D entered into a contract with Dashiell (P) for construction
of the proposed renovation. The price was $3,075,383.00 to furnish all labor, equipment,
materials, and services, and perform all of the work necessary to renovate and expand a
detention center by a date no later than 425 calendar days after the date of commencement.
The contract provided that liquidated damages of $500 per calendar day would be assessed if
P failed to complete the project within the 425 calendar-day period. The contract allowed
for the incorporation of additional documents intended to form part of the contract
documents. The parties agreed to include American Institute of Architects, General
Conditions of the Contract for Construction, Document A201 (1987), which contains the
provisions of the contract that are the subject of this appeal. On March 22, 1994, P
received a Notice to Proceed. P began to encounter construction delays for which it
requested an extension. A sixty-day extension of time was granted. The new completion date
was July 21, 1995. No further completion date extensions were granted. Ultimately,
construction of the project was not completed by the required date of July 21, 1995. By
letter dated July 15, 1996, P submitted a claim in accordance with section 4.3 of the
General Conditions of the Contract for Construction. P sought a change order extending the
contract completion date by 522 days and increasing the contract price by $1,061,038.00 for
delays incurred up to and including June 20, 1996, allegedly due to architectural and
engineer design deficiencies, weather delays, and concealed or unknown conditions.
Furthermore, in a letter dated December 16, 1996, respondent made another claim for
additional time and financial compensation resulting from delays, which were incurred after
June 20, 1996. The County has occupied the renovated detention center since June 6, 1996. P
brought suit basing its claims on quasi-contract and unjust enrichment against D. The court
held that summary judgment for D on the quasi-contract and unjust enrichment claims was
proper, as quasi-contract and unjust enrichment did not apply when there was an express
written contract. P appealed to the Court of Special Appeals. The Court of Special Appeals
reversed the circuit court's decision to grant summary judgment on P's quasi-contractual
claim for unjust enrichment. D appealed.
ISSUE:
RULE OF LAW:
HOLDING AND DECISION:
LEGAL ANALYSIS:
Get
free access to the entire content for Mac, PC or Online
for 2-3 days and free samples
of all kinds of products.
for 2-3 days and free samples of all kinds of products.
https://bsmsphd.com
© 2007-2016 Abn Study Partner
No comments:
Post a Comment