S.J. GROVES & SONS COMPANY V. WARNER COMPANY
576 F.2d 524 (3rd Cir. 1978)
NATURE OF THE CASE: This was a dispute over the losses suffered by a breach of contract.
Groves (P) Plaintiff appealed from a judgment, which awarded damages to Warner (D) but
denied P's requested amount in an action where P claimed extensive losses as a result of D's
failure to deliver under the contract.
FACTS: Groves (P) was awarded a subcontract for the placement of a bridge's concrete
decks and parapets. P contracted with Warner (D) for the delivery of ready mix concrete. The
contract called for the delivery of 35,000 cubic yards at a rate of 40 cubic yards per hour.
The agreement was executed in March 1970. The first concrete was delivered to the site in
July of that year. Progress was hindered by three lengthy strikes in the spring and summer
of 70, 71, and 72 which postponed the completion of the contract from July 1972 to October
1972. Work was also delayed by rejection of concrete that did not meet state specifications.
The total number of rejections was well within those contemplated by the contract. The
general plan was to make pours in the morning and then to construct parapets in the
afternoon. This was frustrated by D's failure to make deliveries in compliance with P's
instructions. As a result, deck pours were extended into the afternoons and evenings and
this created overtime labor expenses. P was desperate and tried to find other sources but
could not as the only other company was not certified to do state work and had limited
production capabilities. D continued to assure P that deliveries would improve. Work was
even stopped because of the poor quality of D's performance. Based on that work stoppage and
assurances from D, deliveries improved significantly although they still failed to meet P's
instructions. Eventually another supplier was certified but P declined to use them despite
their assurances that they could meet P's schedule. P filed a suit for its heavy losses for
D's failure to deliver adequate supplies at the scheduled times. The court found that D had
acted in bad faith by deliberately over committing its ability to manufacture and delivery
enough concrete. The court also ruled that P, as of July 12, 1972, had an obligation to use
the new qualified supplier in order to mitigate the effects of D's poor performance. As a
result, the court did not award all the overtime pay after July 12, 1972. P got the judgment
for $35,401.38. P appealed as a large part of its claims were denied; P only got 25%of the
cost of removing an unacceptable deck panel and no overtime after July 12, 1972.
ISSUE:
RULE OF LAW:
HOLDING AND DECISION:
LEGAL ANALYSIS:
Get
free access to the entire content for Mac, PC or Online
for 2-3 days and free samples
of all kinds of products.
for 2-3 days and free samples of all kinds of products.
https://bsmsphd.com
© 2007-2016 Abn Study Partner
No comments:
Post a Comment